SMW4 Notification

Dear All,

Please be informed that as a part of UG5, post successful demonstration of ATEQ adjustment on Seg-1 Express path through ASN lab tool, MW is planned to demonstrate A-TEQ adjustment & optimization through ASN SN10.3 in each DLS of Seg-1. Maintenance window approved by TWG-Co Chair, mail attached for reference.

Activity will be performed in Cox-Chennai as per below schedule:

__Maintenance Window : 16:00 UTC/16th March 2018 to 4:00 UTC/17th March 2018.

Action plan to be implemented in MW : Step 1 - Disconnection of ASN SLTE from Line & Connection of Fujitsu to extract current A-TEQ position.__

Step 2 - Reconnection of ASN SLTE to the line and A-TEQ adjustment/optimization.

Traffic status during activity : Traffic will be down during Step -1.

During Step-2 traffic will be on High Risk (intermittent errors, flap or down can be observed).

More updates to follow.

Reference SMW4 TT : 26PAN160218